Pre-Test Preparation

1 of 6

Tasks to complete before commencing the load test, ensuring a safe and efficient process.

Scheduled Test Date

Scheduled Test Time

Generator Model

Generator Serial Number

Generator Rated Power (kW)

Notify Relevant Personnel?

Any Pre-Existing Generator Issues?

Load Bank Test Plan (if applicable)

Generator Start-Up & Initial Checks

2 of 6

Verification of generator starting procedure and initial operating conditions.

Test Date

Start Time

Ambient Temperature (°C)

Generator Voltage (Volts)

Generator Frequency (Hz)

Generator Start Procedure Followed?

Observations during Start-Up (e.g., unusual noises, vibrations)

Generator Oil Level

Coolant Level

Load Bank Application & Monitoring

3 of 6

Procedure for applying load and monitoring critical parameters during the test.

Initial Generator Load (kW)

Load Bank Increments (kW)

Load Bank Step Duration (minutes)

Load Bank Connection Type

Voltage (Volts)

Frequency (Hz)

Temperature (Generator Head - °C)

Fuel Consumption Rate (Gallons/Hour)

Observations during Load Application

Performance Evaluation & Data Recording

4 of 6

Assessment of generator performance against established benchmarks and documenting results.

Generator Load (kW)

Voltage (V)

Frequency (Hz)

Fuel Consumption (Gallons/Hour)

Exhaust Gas Temperature (°F)

Oil Pressure (PSI)

Generator Performance - Visual Assessment

Notes on Generator Performance & Observations

Data Logging Graph (Voltage, Frequency vs. Time)

Cool-Down & Generator Shutdown

5 of 6

Proper procedures for reducing load and safely shutting down the generator.

Load Reduction Rate (kW/min)

Time to begin load reduction

Generator Running Time During Cool-Down (Minutes)

Cool-Down Procedure Followed?

If Modified Procedure Used, Explain Deviation:

Time of Generator Shutdown

Shutdown Sequence Normal?

If Shutdown Sequence Abnormal, Describe:

Technician Signature (Cool-Down & Shutdown)

Post-Test Inspection & Reporting

6 of 6

Inspection of the generator and associated equipment, followed by comprehensive report generation.

Summary of Test Results

Overall Generator Performance Rating (1-5, 5 being Excellent)

Abnormalities Observed (Select all that apply)

Detailed Description of Any Abnormalities

Attach Generator Performance Graphs

Date of Next Scheduled Load Test

Technician Signature

Technician Name